Packaged Salad Production and Distribution Plant - Indiana

Project Description: 

Major Location Factors:

  • Refrigerated rail car availability
  • Convenient access to highways / major Midwest markets
  • Competitive local wage and benefit practices
  • High-quality and ample water supply
  • Available sanitary sewer capacity including effluent discharge
  • State and local incentive programs including building retrofit funds

Austin Services Provided:

  • Community and Property Selection
  • Due Diligence
  • Incentives Negotiation
  • Design-Build Retrofit

 

Project Stats: 

Project Investment: $9.8 Million
Labor Requirments: 150 Employees
Site Size: 20 Acres
Building Size: 200,000 SF

Location: 

Original Search Area: Illinois, Indiana, Ohio, Missouri, Kentucky
Final Location: Selected existing building in Plymouth, IN

Share